PROJECT AUTHORIZATION PACKET ID: PMT-GPWY
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
8022203D      80222 15
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER


0757130

06-00014
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
MI
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL STATE LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
6-14 D 1200 FD52 2022 2022 L01E $20,000.00
CURRENT FUNDING REQUEST TOTAL: $20,000.00
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $0.00
DESIGN $7,039,000.00
UTILITIES $1,164,493.00
R/W $12,100,000.00
CONSTRUCTION $53,514,340.00
NON-HIGHWAYS $0.00
  Total: $73,817,833.00
REMARKS: THIS MODIFICATION PROVIDES ADDITIONAL FD52 NHPP FUNDS FOR DESIGN, TOLL CREDIT MATCH.
 
Project Approval Recommended By:
James Ballinger   3/2/2022
Signed and Approved by:
Jim Gray   3/2/2022
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
06-00014.00 BOONE


I-75 I 75 MI ADD AUXILIARY LANES ON I-71/75 FROM KY-536 TO US-42 (NB & SB) AS PER THE INTERCHANGE JUSTIFICATION STUDY (IJS).(10CCR)(12CCR)